Illustrative image – not actual.Work on six lane Vadakkencherry--Mannuthy expressway in Kerala has come to a halt due to unavailability of funds. Consortium of seven banks refused to oblige and provide funds for work as milestones fixed for utilisation of credit remains unachieved.
The work on the 28.5 km stretch was scheduled to start in October 2010 and was to be completed in 30 months, but only 15 per cent has been completed till date.
KMC Construction, the project concessionnaire is executing the project on DBFOT basis under NHDP-III. According to KMC the refusal of the banks to lend money to the project has resulted in serious shortage of funds.