Illustrative image – not actual.Power utility, Tamil Nadu Generation and Distribution Corporation (TANGEDCO) has entered into a memorandum of understanding with V O Chidambaranar Port Trust, Tuticorin, for the upgradation of Coal Jetty I and II.
Jetty I &Jetty II will increase in capacity from 6.25 million tpa to 24 million tpa. The project will benefit TANGEDCO as it will be able to handle an additional volume of coal cargo for the upcoming power plants in Uppur and Kadaladi in Ramanathapuram district of Tamil Nadu.
Also, there will be quicker turnaround of vehicles with the deployment of high tech handling equipment like two ship unloaders, each with a minimum capacity of 2,000 tonne per hour, and a high capacity conveyor system of 4,000 tonne per hour.
The estimated cost of upgrading Coal Jetty I & II is around Rs 800 crore. Initially Coal Jetty-I will be revamped by constructing a new Coal Jetty I of 300 mtr x 25 mtr along with repairs of the existing CJ-I in around 24 months. Once completed CJ-II will be upgraded.