Illustrative image – not actual.The Uttarakhand Government has given permission to Hyderabad-based GVK Power to mortgage lease rights to raise funds for the 330 MW Alaknanda hydel power project.
The company is developing the project on the river Alaknanda near Srinagar town in Uttarakhand. The state government permission has enabled GVK to raise funds from the consortium group of lenders for the Rs 2,100 crore project. It also aims to complete the project in 2011 instead of the scheduled completion in 2012. The state government is likely to get 12 per cent of the power from the Alaknanda project free of cost as part of royalty.
Meanwhile, GVK has also agreed to elevate the Dhari Devi temple to a height of 19 mtrs, which is expected to be drowned under the reservoir of the dam. The company will spend Rs 10 crore for the elevation of the temple and creating other facilities for the locals.