Illustrative image – not actual.On 12 November 2006 Uttar Pradesh government signed power purchase agreements with Reliance Energy, GVK Group and Lanco Kondapalli for three power projects.
While Reliance Energy signed the PPA for the 600 MW Rosa power project, GVK and Lanco sign agreements for the 330 MW Srinagar hydropower project and the 1,000 MW Anpara C, respectively. The three projects are expected to be completed within four years.
The 1,000 Mw Anpara C project was awarded to Lanco Kondapalli after it outbid Reliance Energy and Essar Group. NTPC has been appointed as the consultant for the project. The 600 MW Rosa power plant in Shahjahanpur district of Uttar Pradesh which was with the AV Birla group, has been taken over by Reliance Energy.
The other projects sanctioned in the state includes:
| Project | Capacity (MW) |
Cost (Rs. crore) |
Completion |
| Harduaganj Thermal Power | 2x250 | 2,000 | 2010-11 |
| Parichha Power Project Stage III | 2x250 | 2,000 | 2010-11 |
| Anpara 'D' Coal Based Power | 2x500 | 5,000 | 2010-11 |
Also See: