Uttar Pradesh govt clears Gorakhpur's Light Metro railIllustrative image – not actual.
The government of Uttar Pradesh has cleared the Light Metro project. Also known as light rapid transit, Light Metro is a rail transport system with a capacity greater than light rail, but lower than the typical heavy-rail rapid transit system.
 
The Gorakhpur Light Metro project, which is estimated to be completed by 2024, will span almost 28 km with two elevated corridors. While one elevated corridor would span 15.14 km comprising 14 stations, the other corridor would run 12.70 km and consist of 13 stations.
 
The government also gave its nod to the detailed project report (DPR) of the project.
 
In the 2020-21 Uttar Pradesh Annual Budget, the state government had made a provision of Rs 900 for the under-construction Delhi-Meerut Regional Rapid Transit System. 
 
Besides, Rs 286 crore and Rs 358 crore were allocated for the Agra and Kanpur Metro projects respectively. Currently, Metro rail services are being run in Lucknow, Ghaziabad and Noida cities.
 
The work on the Kanpur Metro project is progressing at a fast pace. Even during the post-lockdown period, strategic execution helped the Uttar Pradesh Metro Rail Corporation (UPMRC) in maintaining the workforce for construction of the nine km priority corridor of Kanpur Metro, which has become the first Metro project in India where pre-cast double T-girders are being used for constructing the concourse level of the stations.
 
On 31 August 2020, the European Investment Bank (EIB) had signed a loan contract for Kanpur Metro for EUR 650 million (Rs 5,552 crore) through a virtual signing ceremony. EIB is expected to evaluate the Agra Metro soon for a similar credit facility.
 
Meanwhile, the government has expedited land acquisition for the Kanpur and Agra Metro projects, which are collectively estimated to cost Rs 19,000 crore. 
 
In Agra, 21 ha of land, notified as protected forest, will be released for the Metro project, while another land will be notified as protected forest in the district to compensate for green cover. Besides, eight ha of land under the possession of the 15th company of provincial armed constabulary (PAC) will be provided for the Metro project.