Uttar Pradesh Government approves 2 power projectsIllustrative image – not actual.

The Uttar Pradesh Government has approved setting up of two power plants, one each in thermal and hydro sector.

The state government approved Obra-C thermal power station which will be located in Sonebhadra district with a capacity of 1,000 MW (2x500 MW). The Rs.6,175 crore project will be developed by the state government with a debt:equity ratio of 70:30. The state government will contribute the entire equity and the balance 70 per cent will be raised from financial institutions and banks through loans. The government has the necessary 200 ha to set up the power plant. Around 37 cusec water will be available from Rihand river while coal linkage has also been approved from the Chendipara Coal block.

The state has also given its approval for a 30 MW Dhukwa hydro power project about 30 kms from Jhansi in Lalitpur district of Bundelkhand region on river Betwa. This project will be developed by Tehri Hydro Development Corporation (THDC).