Utkal-E captive coal block at Angul district of Orissa, is likely to be operational by December 2014.

 

The block has already failed to meet several deadlines for want of various clearances. The proposed coal block has been allotted to NALCO in August 2004, to meet coal requirements of four of its captive power plants. The stage-I forest clearance is yet to be received for the project due to issues relating to forest rights on nearly 71 acre out of 488.53 acre of forest land required for the project.

 

The process for acquisition of government as well as private land, forest clearance, construction of R&R colony and appointment of MDO (mine-developer-operator) is going on.

 

The company has already achieved clearance of mining plan, wildlife and environment, as well as Coal Ministry's approval for mining lease. The delays have also led to 21 per cent cost escalation for the project, raising the cost to Rs 338 crore from the previous estimate of Rs 280 crore.

 

The coal block is estimated to hold 67.49 million tonne reserves.

 