Illustrative image – not actual.The Rs.55 crore expansion project of
United Provinces Sugar Co. Ltd, which was supposed to be completed by September
2001, has been delayed by a year.
The project aims at expanding the sugar
capacity from 2,500 tonnes of cane crushed per day (tccpd) to 5,000 tccpd.
Besides, the bagasse-based captive power plant would also see an enhancement in
capacity from 3.5 MW to 6 MW.
Of the total project cost of Rs.55
crore, around Rs.25 crore has been spent till December 2000. The sugar capacity
of the company has since been partially expanded to 3,500 tccpd. The company’s
sugar mill is located in the Kushinagar district of Uttar Pradesh.
The company embarked on the expansion
programme in July 1998 and had then envisaged completion by September 2001.
The project is being funded by
financial institutions (to the extent of Rs.26.75 crore), the Sugar Development
Fund (Rs.21.4 crore) and internal generation (Rs.7.35 crore).