Illustrative image – not actual.This is a status report of the Upper Krishna Project, being implemented by Krishna Bhagya Jala Nigam, as on 31 March 2002.
Narayanpur dam and allied works – All works
under this programme have been completed.
Almatti Dam and allied works – This programme
too comprising Left Bank Earth and Masonry Dam (EL 528.800 m), Spill
Way (EL 509.016), Right Bank Masonry Dam (Power Dam and Non-overflow
Section) and Providing Gates (26 nos.) has also been complete in all
respects.
Narayanpur Left Bank Canal – The Main canal (78 km) with an irrigation area of 47,233 ha, Shahpur
branch canal (76 km) with an irrigation area of 1,22,120 ha and Mudbal
branch canal (50.80 km) with an irrigation area of 51,000 ha under this
programme have been completed.
However, Indi branch canal (172 km), from 0 to 64 km has been
completed in all respects and water has been let out into the canal up to field
outlets. Water has been allowed on trial basis from km 65 to 133. Meanwhile,
earthwork from km 134 to 174 have been completed, while work on the rest is in
progress.
In case of the Jewargi branch canal (86.36 km) too, earthwork in
the reach from km 0 to 86.36 including lining up to km 70 has been completed.
Further, lining work from km 71 to 86.36 is in progress. Out of 196.73 km
length of distributary network, 190 km has been completed and water has already
been let out on trial basis up to km 70 of the main canal.
Narayanpur Right Bank Canal (95 km) – Excavation work in reaches from km 0–90, including lining
packages from km 21 to 90 are completed. Earthwork in reaches from km 91 to 95
is in advanced stages of completion. Out of 364 km length of distributary
network, 230 km length has been completed and water has already been released
on trial basis up to km 39 of the main canal and distributary 1 to 7.
Almatti Left Bank Canal (103 km) – Headwork has been completed and the pumps have been test run. The
system is ready for commissioning. The canal works from km 0 to 40 are almost
completed, including Hullur Nala Aqueduct at km 12. Work from 41 to 60 is in
progress. Further, work from km 61 to 67 has been awarded on tender basis.
Meanwhile, preliminary survey and investigation from km 68 to the end of stage
II has been completed and alignment has also been approved up to km 80.
Almatti Right Bank Canal (128.50 km) – Jackwell up to 540 m and erection of pumps has been completed.
While plastering and flooring work, and canal works from km 0 to 67.50 is in
progress.
Mulwad Lift Irrigation Scheme (128.50
km) – The first jackwell near Baluti has
been raised up to motor floor level and further work is in progress. The
casting of motor floor level is completed. The contracts for supply of EOT
crane, sub-station works for this structure have been awarded. Excavation work
on the second jackwell near Hanumapur is in progress. The lead off canal
is completed in all respects. Work on the East canal from 0 to 17.40 is in
progress, while work on the West Canal from km 0 to 54 is in progress.
The distributary planning of both East and West canals are under progress.
Rampur Lift Irrigation Scheme (37.50
km) – Headwork for Stage – I is in progress, while
the intake channel has been completed. The installation of Navali pumping
station for power supply, erection of pumps and 33 KV sub-station for Navali
Lift is under progress.
Indi Lift Irrigation Scheme (96.50 km) – The work of construction of Head Regulator at km 0.015 and intake canal
including Super Passage / CTC at km 0.42 has been completed, while other work
is still under progress.