Illustrative image – not actual.K S Eshwarappa, Minister of Energy, Karnataka, inaugurated 220 kV Double Circuit line between Kemar in Karkala taluk and Udupi Power Corporation Ltd (UPCL) distribution network at Nandikoor near Udupi on 22 September 2009.
Around 500 MW of power generated from the first unit of UPCL is expected to be taken to the main grid by 31 March 2010.
The present transmission line with a length of 22.7 km has been executed at a cost of Rs 33.21 crore. The company is in the course of installing another line to Shantigrama, at a cost of Rs 396.39 crore.