Illustrative image – not actual.Uttar Pradesh Power Corporation (UPPCL) has cancelled the PPAs with six firms for delay in setting up their projects.
The six plants with a combined capacity of 80 MW belong to Adani Green Energy, Sahastradhara Energy, Pinnacle Air, Awadh Rubber Prop Madras Elastomers, Technical Associates and Sudhakara Infratech.
The decision was taken in the case of those companies which had failed to complete their projects on time. According to the agreements signed in 2015, the developers had to complete the projects by January 2017. The deadlines were extended twice; first till March 2017 and then till September 2017.
Fifteen developers had signed contracts for the 215 MW solar auction for tariffs ranging between Rs 7.02 per kwH and Rs 8.60 per kwH in December 2015. While some of the developers who had already installed their projects refused to toe the line, others who had not completed their projects yet agreed to scale down the tariffs. It is these developers who have been issued cancellation notices by UPPCL.
The state government had entered into an agreement with 15 companies in 2015 under the 2013 solar power policy. Out of these 15, nine had installed solar power plants with a total capacity of 135 MW, while six companies, with an aggregate capacity of 80 MW, did not work as per the said agreement.