Illustrative image – not actual.The US based Unocal Corporation, has pulled out of
the 700 MW, gas based, Bidadi power project, in which the company had a 26 per
cent stake through its subsidiary, Unocal Bharat.
KPC Bidadi Power Corporation, a joint venture between Unocal Bharat and Karnataka Power Corporation (KPCL), was to implement the project. Now, with the Unocal withdrawing support, KPCL's stake in the project would go up from 25 per cent to 51 per cent. The remaining 49 per cent stake is held by institutions and the public.
Not giving details on Unocal’s withdrawal, the Chief
Minister, Mr S M Krishna, stated that that the 3-year period for firming the
project had expired. Further, Mr Krishna also mentioned the state government
would now look at other options for implementing the project.
It may be mentioned that the project was initially
planned as a 200 MW liquid fuel based power project. The project cost was then
estimated at Rs.800 crore with a debt equity ratio of 70:30 per cent. Later,
however, the project was upgraded to a 700 MW combined cycle plant, to be
implemented at a cost of around Rs.3,000 crore. It was to be fired initially by
naphtha and later by LNG.