Unit VII of Raichur TPS nears completionIllustrative image – not actual.

The 210 MW, unit VII of the Raichur Thermal Power Station, is nearing synchronisation with the completion of the boiler light up. The project, which is being implemented by Karnataka Power Corporation (KPCL), would be commissioned towards the end of December 2002.

 

KPCL has maintained the capital cost of the project within the techno-economic parameters specified by the Central Electricity Authority. These parameters specify a project capital cost of Rs.613 crore.

 

Taking the capital cost into consideration, it may be assumed that the tariff is unlikely exceed Rs.2.40 a unit.

 

On commissioning the project, an additional 5 million units a day would be provided. This implies a plant load factor of over 95 per cent.

← All latest storiesBack to top →