Illustrative image – not actual.The 210 MW, unit VII of the Raichur Thermal Power Station, is nearing synchronisation with the completion of the boiler light up. The project, which is being implemented by Karnataka Power Corporation (KPCL), would be commissioned towards the end of December 2002.
KPCL has maintained the capital cost of the project
within the techno-economic parameters specified by the Central Electricity
Authority. These parameters specify a project capital cost of Rs.613 crore.
Taking the capital cost into consideration, it may be
assumed that the tariff is unlikely exceed Rs.2.40 a unit.
On commissioning the project, an additional 5 million
units a day would be provided. This implies a plant load factor of over 95 per
cent.