Unit IV of Mundra power plant syncronisedIllustrative image – not actual.

Adani Power on 24 November 2010, syncronised its forth unit of 330 MW capacity at Mundra in Kachchh district of in Gujarat. With this the company achieved total generation capacity of 1,320 MW of coal fired power generation.

The company is setting up 4,620 MW power plant at Mundra that includes four units of 330 MW and five units of 660 MW. Three units of 330 MW have already been commissioned. The 660 MW units are based on energy efficient and environment friendly super critical technology.

The company has arranged for transmission of power from the Mundra power station by laying a 440 kV transmission line from Mundra-Dehgam covering 430 km length and about 500 kV HVDC line from Mundra to Mohindergarh covering 1,000 km length.