Unit-II of steam turbine combined cycle power commissionedIllustrative image – not actual.

Pragati Power Corporation has begun commercial operations at Unit-II of the steam turbine combined cycle power project (Pragati-III) at Bawana, in North West Delhi.

 

With the commissioning of Unit-II of the steam turbine combined cycle, the 1,500 MW power project has become fully operational.

 

The 1,500 MW, gas-based power project (Pragati-III) has been set up in six units, each having a capacity of 250 MW.  Out of six, four units are gas based and two units are steam based.

 

In May 2013, gas turbine combined cycle power Unit-IV was commissioned. On 24 March 2008, Manmohan Singh, Prime Minister of India, laid the foundation stone for the project.

 