Illustrative image – not actual.The power plant is part of KenGen’s green energy development agenda aimed at delivering 721 MW renewable energy by year 2020, at an investment close to about USD 1.3 billion. The project is funded by the Japan International Co-operation Agency (JICA) and the government of Kenya.
The engineering, procurement and construction (EPC) contract for this project was executed by three companies: Mitsubishi Corporation, whose role was to supply equipment for the geothermal power plant; Mitsubishi Hitachi Power Systems was responsible for transporting equipment from the eastern port of Mombasa to the site where the plant is located in western Kenya. H Young & Company (HY) was mandated to supply some of the parts needed to equip the steam plant.
The first unit of this plant was commissioned in July 2019 by the Kenya Electricity Generating Company (KenGen), the independent power producer (IPP) developing the project in western Kenya. Both Unit-I and -II will supply a total of 160 MW electricity and absorbing 500 tonne of dry steam per hour.