Illustrative image – not actual.Haryana Power Generation Corporation Ltd's (HPGCL) Unit I of 1,200 MW Rajiv Gandhi Thermal Power Project (RGTPP) at Khedar in Hisar district of Haryana is likely to begin power generation by December 2009.
Currently, the final commissioning activities of 600 MW Unit I of RGTPP are underway. An overall progress of around 88 per cent have already been achieved and in project engineering and procurement a progress of 93.1 per cent and 92.2 per cent, respectively, have been achieved.