Unit-I of Phase I of Rosa power project goes on-streamIllustrative image – not actual.

The Unit-I of Phase I of 600 MW (2x300 MW) Rosa power project in Shahjahanpur district of Uttar Pradesh has commenced power generation on 28 December 2009.

The Phase-I of the Rosa power project involves setting up of 2x300 MW power units, of which Unit-I has commenced power generation and the Unit-II is expected commence power generation in next few weeks. Phase-II is likely to go on stream by March 2012.

The 1,200 MW coal based project of Reliance Power comprises two phases of 600 MW each. The project is being set up at a cost of Rs 6,000 crore.

The fuel for the project is to be transported from Central Coalfield in Jharkhand under a long-term contract valid for the entire plant life of 25 years.

Also See:

Rosa power plant to complete by end-December (08-Dec-09)

Related Links:
Project profile

← All latest storiesBack to top →