Illustrative image – not actual.The Unit-4 of
Rajasthan Atomic Power Station at Rawatbhata near Kota began commercial
production on 25 December 2000, after having been synchronized to the Northern Grid
on 17 November 2000.
The 220 MWe
Pressurized Heavy Water Reactor (PHWR) had achieved criticality on 3 November
2000, after regulatory clearance from the Atomic Energy Regulatory Board
(AERB).
RAPP Unit-4 achieved
criticality in less than a year of criticality of Unit-3 that did so on
December 24, 1999. RAPP Unit-3 was synchronized to the grid on March 10, 2000.
With this, the
aggregate capacity of the four units of Rajasthan Atomic Power Station has gone
up to 790 MWe and that of the fourteen nuclear reactors of Nuclear Power
Corporation of India, to 2720 Mwe.