Union Ministry of Environment delists Bhadradri Thermal Power StationIllustrative image – not actual.

The Union Ministry of Environment has delisted Bhadradri Thermal Power Station from the list of projects awaiting environmental clearance.

The proposed project was the 1,080 MW Thermal Power Station at Manuguru in Telangana. The foundation stone for the proposed project was laid by Chief Minister, K Chandrashekar Rao, on 28 March, 2015.

The state government set aside Rs 7,200 crore for the proposed project and assigned its construction to Bharat Heavy Electricals. Work on the project started to bring the project on stream by March 2016.

However, the project faced a road block as the Human Rights’ Forum lodged a complaint against it with the National Green Tribunal.

With the environmental committee’s tenure coming to an end, a green signal was given to the project on 18 March, 2016.

However, the Union Ministry of Environment disapproved the project and announced removal of it from the list of projects awaiting environmental clearance.

 

← All latest storiesBack to top →