Illustrative image – not actual.The Union Ministry of Railways has sought approval of the Union Cabinet to build three new dedicated freight corridor (DFC) networks at a total investment of about Rs three trillion.
While the East-West Corridor (2,328 km) will be built between Kolkata and Mumbai, the North-South Corridor (2,327 km) is planned between Delhi and Chennai and the East Coast Corridor (1,114 km) between Kharagpur and Vijaywada.
The Indian Railways’ DFC project involves constructing five freight corridors across the country. The railways through its arm, the Dedicated Freight Corridor Corporation of India (DFCCIL), is already building the first two freight corridors -- Eastern Freight Corridor from Ludhiana to Dankuni (1,856 km) and Western Freight Corridor from Dadri to Jawaharlal Nehru Port (1,504 km) — at a total cost of Rs 81,000 crore.
The ministry intends to complete more than 60-70 percent of the work in the two corridors by FY20 and make them fully operational by 2021. The three new DFCs will cover 5,769 km.
The preliminary engineering and traffic system study of these corridors has already been completed. After the Cabinet approval, DFCCIL will undertake a detailed project planning, including plans for land acquisition.
The first section of the eastern DFC --200 km stretch from Bhadan to Khurja and western DFC, and another 200 km from Rewari to Madar -- has been completed. Around 1,000 km of DFC, including western DFC connecting states such as Haryana, Maharashtra and eastern DFC connecting Punjab and West Bengal, is expected to be operational in 2019.