Underground tunnelling of North Chennai corridor completedIllustrative image – not actual.

The underground tunnelling of the North Chennai corridor has been completed ahead of schedule.

Chennai Metro Rail (CMRL) completed the underground tunnelling as part of phase-1 extension of the North Chennai corridor. The tunnelling work for the project began in February 2017 and was completed five months ahead of schedule.

Work on the second tunnelling is expected to be completed in a month. Afcons Infrastructure carried out the tunnelling work.

The tunnelling work was taken up beneath the railway tracks at Washermenpet besides crossing under 480 buildings and 310 bore wells, of which 10 were open wells.

Around 30 percent of the work for stations on the stretch has been completed, while the signalling work is expected to commence by 2017 end.

Both underground and elevated work is expected to be completed by 2019.

 