Illustrative image – not actual.The partially depleted gas reserves of the Cambay basin, off
the Gujarat coast, are proposed to be converted into an underground gas storage
station (UGS) with an investment of $250 million (approx. Rs.1,125 crore). The
investment would be made over a four-year period.
The three billion cubic metres gas fields, which were
discovered by the Oil and Natural Gas Corporation in 1958, are depleted by
50-60 per cent and would require fresh infusion of 1.5 billion cubic metres of
gas to become technically viable.
Gaz de France had submitted a pre-feasibility report on the project to the Gujarat State Petroleum Corporation (GSPC) in October 2000 and an advanced report in December 2000. The GSPC would now be required to surrender the gas fields to the Union Ministry of Petroleum and Natural Gas. After this, the fields would be returned to the Gujarat State Government, which would subsequently approve the UGS project.