Illustrative image – not actual.On 25 July 2008, Sutlej Jal Vidyut Nigam (SJVNL) implementing the 412 MW Rampur hydroelectric power project achieved a milestone by completing underground excavation of 149.4 mtrs deep, 7.15 mtrs dia pilot, of 38 mtrs dia surge shaft ahead of schedule.
Last blast of pilot was performed by Executive Director for the power plant , Mr.V K Sharma on 24 July 2008, at Bayal. The construction of surge shaft was one of the most critical activity of Rampur power project which required excavation of Pilot of 7.15 mtrs dia first from the top to facilitate the excavation of 38 mtrs dia surge shaft. Open excavation of about one lakh cubic meter in surge shaft was started during April 2007 and completed during September 2007. Underground excavation of pilot was then taken up on 14 September 2007 and depth of 149.4 mtrs was completed in 11 month time.