Underground corridor proposed between CSMT-ThaneIllustrative image – not actual.
The Railways has proposed a new underground corridor between Chhatrapati Shivaji Maharaj Terminus (CSMT) and Thane, along with two other railway corridors in the Mumbai Metropolitan Region (MMR), under Phase-4 of the Mumbai Urban Transport Project (MUTP 4).

The proposal has been sent to the State government and the Railway Board. The underground railway project will be built jointly by the Railways and the government of Maharashtra and executed by a special purpose vehicle (SPV) such as the Delhi Metro Rail Corporation (DMRC) or the National High Speed Rail Corporation (NHSRC).

According to the proposal, 60 percent of the project cost is expected to be met through financing from multilateral funding agencies or borrowings from the market. The remaining 40 percent will be borne equally by the Railways and the State government, which has been the norm for all MUTP projects.

The completion cost of the project is pegged at Rs 17,962 crore. The project is expected to take five years to execute and proposed to start by 1 April 2020 and completed by 31 March 2025.

The other two projects that are part of MUTP 4 were earlier part of the Rs 33,690 crore MUTP 3A -- the new corridor between Virar and Panvel and the elevated fast corridor between CSMT and Panvel. The Railways is planning to terminate the corridor at Vasai, while the elevated fast corridor will remain the same.

The three projects together will cost around Rs 34,000 crore. The proposal of the underground corridor states that it will have only five halts and will be built along the lines of a Metro. It aims to reduce travel time to around 21 minutes from 35 to 40 minutes.

The state cabinet cleared the proposal for the underground extension of the corridor, which will run from Wadala to General Post Office near CSMT, and is expected to cost around Rs 8,000 crore.