Under sea tunnel for bullet train likely to be completed by August 2022Illustrative image – not actual.

Work on the bullet train project is underway in Mumbai and Thane. The under sea tunnel, which is part of the project, is likely to be completed by 15 August 2022.

Presently, work on static refraction is being done along with the Japanese agency Kawasaki Geological Engineering Company.

The tunnel will be constructed 25 mtr to 40 mtr deep from the sea bed.

The data acquisition work on the tunnel project commenced on 11 December 2017 and is likely to be completed by 24 December 2017.

The Japanese professionals from Kawasaki Geological Engineering Company are expected to submit their report on the data acquisition to their lab in Japan and the final report will be submitted in January 2018.

The bullet train between Ahmedabad and Mumbai will run a total length of 508 km, of which 21 km will be covered in the tunnel under sea.

The under sea tunnel is expected to entail an investment of Rs 3,500 crore.