UltraTech Cement plans Rs.2,700 crore capexIllustrative image – not actual.

UltraTech Cement is planning capital expenditure of Rs.2,700 crore to augment its cement manufacturing capacities and install captive power plants for a period of three years.

The plan includes investing of about Rs.1,424 crore, including Rs.844 crore for installation of captive power plants at its units in Gujarat and Chhattisgarh. Around Rs.308 crore will be invested for de-bottlenecking of its plants.

The company at present has a capacity of 17 million tpa with five integrated cement plants, supported by five grinding units and some captive power plants.

The company will be additionally investing Rs.1,274 crore towards a 4 million tpa capacity expansion at its Tadipatri plant in Andhra Pradesh. This is inclusive of setting up of a 1.3 million tpa split grinding unit and a 46 MW captive thermal power plant at that location.

Also See:

ULtra Tech plans 92 MW power plant (25-Aug-05)