Ultra mega power project series: EOIs formality might be omittedIllustrative image – not actual.

To shorten the gestation period of the proposed ultra mega power projects, the power ministry has decided to skip the EoIs stage for those coming up in Ib valley in Orissa and at Krishnapatnam in Andhra Pradesh.

The Power Finance Corpn., the nodal agency for developing these projects, will now directly issue RfQs by July 2006 leading to faster selection of developers.

In the earlier activity schedule for ultra mega projects were as follows:

  • Notice for EoIs followed by their submission.
  • Issue of RFQ documents followed by submission. 
  • Issue of request for proposal (RFP) documents followed by submission. 
  • Last stage was the selection of a developer, leading to the transfer of the special purpose vehicle created for the project to the developer.

The earlier approach wanted to call applications from developers are -  Akalatara (Chhattisgarh) and Tadri (Karnataka) after Sasan (Madhya Pradesh), Mundra (Gujarat) and Girye (Maharashtra).

The Akaltara project has been put on hold, due to the Chhattisgarh government's demand for 12 per cent free power and complete allocation of 4,000 MW from the proposed project.

For the ultra mega power projects in Sasan, Mundra and Girye, EOIs have been submitted and RfPs for Sasan and Mundra will  be issued on 1 July 2006, followed by their submission by 30 September 2006. Selection of the developer and transfer of special purpose vehicles for the two projects are slated to be completed by 31 December 2006.