Illustrative image – not actual.Uttarakhand Jal Vidyut Nigam (UJVNL) in JV with GAIL is planning to set up gas based power plants in Uttarakhand.
The company plans to invest Rs 2,500 crore to set up two gas based power plants. UJVNL has got 50 acre in Kashipur and has identified another 55 acre in Haridwar for the power plants. In this regards, in June 2011, the company had signed an MoU with GAIL for two gas based power plants of 350 MW each. The majority of the power from these power plants will be sold to Uttarakhand through a long-term PPA. The 182-km Karanpur-Moradabad-Kashipur-Rudrapur-Pant Nagar natural gas pipeline is at final stages of completion. The design capacity of the Rs 250-crore pipeline will be 2.5 mmscmd. The pipeline will supply gas to upcoming power plant in Kashipur in Uttarakhand and to other industrial customers in Moradabad, Kashipur and Rudrapur and for City Gas Distribution in Moradabad. Another gas pipeline for Haridwar power plant is also at advance stage. Both the pipeline projects are slated to be completed by 2015-16.