Illustrative image – not actual.The Central Electricity Authority has accorded
techno-economic clearance to the 100 MW (2x50 MW) Uhl hydel based power project
(stage III) in Himachal Pradesh. The run-of-river project is being executed by
Himachal Pradesh State Electricity Board at Khuddar in the Mandi district of
the state.
The Rs.431 crore project would use the water released
from the existing Bassi power house together with the waters of Neri and Rana
streams for power generations.
The project is scheduled for completion by March 2007. The completed plant would generate about 391 giga watt hours (GWh) in a normal year and provide peaking capacity benefit to the power system.