Illustrative image – not actual.The Uganda Electricity Generation Company (UEGCL) has launched an upgrade exercise for three power transmission lines for the start of operations of under-construction Karuma hydropower station.
The transmission lines, in particular, are the 264 km 400 kV Karuma-Kawanda power line that will link a high voltage substation in the power station to another high voltage substation at Kawanda, in the Central Region of the East African country.
The other two lines are the 60 km 400 kV Karuma-Olwiyo power line that will connect the Karuma Power Station to a substation in Olwiyo, Nwoya district, and the 80 km 132 kV Karuma-Lira power line that will link the Karuma power station to Lira.
The Karuma hydropower station, located in the Kiryandongo district in the north-western region of Uganda, is reportedly in the final stages of construction with approximately 98 percent of the entire work complete. The project is being carried out by the Sinohydro Corporation.
Equipped with six 100 MW Francis turbines, the Karuma hydropower station is expected to have a capacity of about 600 MW upon completion.
The electricity generated by the Kurama hydropower plant will guarantee stable, reliable and affordable electricity in Uganda.
With the commissioning of the Karuma power plant, the East African country will reach a capacity of 1,500 MW. Currently, Uganda consumes approximately 600 MW at peak hours.
The government has also revealed that once the plant is commissioned and fully utilised, the weighted generation tariff will reduce from the current US cents 6.47/kWh to US cents 5.34/kWh, indicating 17.65 percent decrease.
The transmission lines, in particular, are the 264 km 400 kV Karuma-Kawanda power line that will link a high voltage substation in the power station to another high voltage substation at Kawanda, in the Central Region of the East African country.
The other two lines are the 60 km 400 kV Karuma-Olwiyo power line that will connect the Karuma Power Station to a substation in Olwiyo, Nwoya district, and the 80 km 132 kV Karuma-Lira power line that will link the Karuma power station to Lira.
The Karuma hydropower station, located in the Kiryandongo district in the north-western region of Uganda, is reportedly in the final stages of construction with approximately 98 percent of the entire work complete. The project is being carried out by the Sinohydro Corporation.
Equipped with six 100 MW Francis turbines, the Karuma hydropower station is expected to have a capacity of about 600 MW upon completion.
The electricity generated by the Kurama hydropower plant will guarantee stable, reliable and affordable electricity in Uganda.
With the commissioning of the Karuma power plant, the East African country will reach a capacity of 1,500 MW. Currently, Uganda consumes approximately 600 MW at peak hours.
The government has also revealed that once the plant is commissioned and fully utilised, the weighted generation tariff will reduce from the current US cents 6.47/kWh to US cents 5.34/kWh, indicating 17.65 percent decrease.