Udhampur-Srinagar-Baramulla railway project cost escalatedIllustrative image – not actual.
The Udhampur-Srinagar-Baramulla railway project cost has escalated to Rs 19,565 crore from Rs 2,500 crore when it was approved in March 1995.

 

This rail project has been delayed by over 16 years and will result in cost overrun of Rs 17,065 crore. It is projected to be completed by December 2018, as compared to its original date of November 2002. As of now, Rs 10,205.04 crore has been incurred on the project.

 

There are several similar projects costing above Rs 150 crore each, which have been delayed due to law and order problems, land acquisitions, environment and forest clearances, fund constraints and contractual issues.

 

The Statistics Ministry is monitoring 738 central sector projects costing Rs 150 crore or more. The projects in sectors including rail, road, power and civil aviation were showing time and cost overrun, as on 1 January 2015.

 

Presently, 232 projects (worth Rs 13.51 lakh crore) with 611 issues are under consideration of the PMG including three resolved projects which have new issues. As many as 57 projects (in PMG worth Rs 4.14 lakh crore) have been closed as no action was required by the PMG.

 

More Project Info:
Udhampur-Qazigund-Srinagar-Baramula BG Railway Line