Illustrative image – not actual.The U-turn flyover is part of the ongoing over Rs 1,000 crore project to ease traffic movement at four major intersections in the city.
The project has been completed almost 17 months ahead of schedule.
The entire project involving construction of four flyovers and three underpasses is expected to be completed by 31 December 2017, almost 15 months ahead of schedule.
Construction work for the project started on 1 December 2016 and the project was to be completed by 31 March 2019 as per the contract.
Two more flyovers at IFFCO Chowk -- a U-turn four-lane unidirectional flyover and another flyover running parallel to the intersection are likely to be opened soon.
Two foot overbridges and pedestrian subways are also being constructed at IFFCO Chowk as part of the project. Two foot overbridges and dedicated tracks for non-motorised transport will also be constructed at Rajiv Chowk as part of the improvement plan for the intersection.