Two wind power projects aggregating 15 MW of KS Oils are scheduled to commission by March 2007.

Speaking to ProjectsToday, company officials said that the company is likely to commission the 13.5 MW (three farms of 4.5 MW each) project in Kachchh district of Gujarat by February 2007. The project would entail an investment of Rs.27 crore. Around 90 per cent work on the project is completed. The DPR was prepared by Suzlon Energy Ltd.

Another 1.5 MW wind power unit at Chhabra in Vadodara district of Gujarat with an investment of Rs.9 crore is scheduled for completion by March 2007.