Illustrative image – not actual.
The supply of coal will improve in FY 2018 as two key rail connectivity projects in Odisha and Jharkhand will become operational, either partially or fully.
The 53.5 km Jharsuguda-Barapali rail link in Odisha is ready except for the 0.5 km stretch. Work on the stretch has been halted due to land hassles.
The railway line will become operational in FY 2018 as the state government has promised to pave the way for evacuation of fuel from the vast Ib Valley reserves in Sundergarh district. The project is financed by Coal India. The cost of the project has increased nearly fourfold to approximately Rs 2,200 crore.
The rail link will improve coal availability by 20 million tpa in the near future. The project will increase coal production by around 80 million tpa.
The execution of the Tori-Shibpur railway project is moving at a slower pace. The project will help the supply of coal from Magadh and Amrapali, which can produce 30-50 million tpa.
The East Central railway has connected Ranchi with Tori. The railway line is expected to reach Bhalubasa by the end of 2017.