Illustrative image – not actual.In order to further strengthen the transmission and distribution network in Kurukshetra district, the Haryana Vidyut Prasaran Nigam (HVPN) and Uttar Haryana Bijli Vitran Nigam (UHBVN) have jointly started various developmental works to be completed at an estimated cost of Rs.1,000 million.
According to Nigam sources, a 220 kV sub-station at Salempur and a 66 kV sub-station Lohara would be set up by Nigam and existing capacity of 33 kV sub-stations at Mathana and Kirmich would be upgraded to 66 kV and 132 kV level respectively. Power Utilities had also approved the augmentation of 132 kV sub-station at Malikpur and 66 kV sub-station at Gangori, where power transformers of 16 MVA capacity each would be installed.
The setting up of new sub-stations and augmentation of existing sub-stations would give way to transmit and supply power from the upcoming Yamuna nagar Thermal Power Plant during the current financial year.