Illustrative image – not actual.The MMRDA has stepped up the construction of the four flyovers coming up on Ambedkar Road in Mumbai in Maharashtra.
On 22 October 2009, the MMRDA has begun construction of the first segment of the 2.4-km Lalbaug flyover, which will connect Bharatmata Junction and Jijamata Udyan. Work on the flyover is likely to be completed before September 2010.
The 780-mtrs Sion Hospital junction flyover is slated to be opened to traffic by December 2009. The MMRDA has already completed structural work on Sion flyover, it is currently undertaking the finishing work.
The construction of Hindmata flyover is on schedule and it is likely to commence operations by end-January 2010. Presently, the segment casting is being completed.
However, work on the Kings Circle and Tulpule Chowk flyovers is pending. According to sources, post completion of the Sion and Hindmata flyovers, construction of the Kings Circle flyover is likely to be taken up in full swing.