Two Metro lines in Mumbai to begin operations in eight monthsIllustrative image – not actual.

Chief Minister of Maharashtra Devendra Fadnavis conducted a review of infrastructure projects in the state. The two elevated Metro lines in western suburbs of Mumbai – Dahisar-DN Nagar Metro 2A and Dahisar East-Andheri East Metro 7 will start operations in the next eight months. Once operationalised, the two lines are expected to cater to more than 16 lakh commuters.

 

The earlier deadline for both networks was 2019-end; only 65 percent of the civil work has been completed for Metro 2A and 68 percent for Metro 7. By 2022, nearly 119 km of additional Metro circuit will be added to the city’s transport network.

The CM also reviewed the Mumbai Trans Harbour Link. Work on laying pillars has begun and the project is expected to be completed in four years. The other works reviewed included railway projects like Wardha-Nagpur, Ahmednagar-Beed-Parli, Wardha-Nanded, Nerul –Belapur-Seawoods-Uran line, Rajapeth and Amravati ROB.