Illustrative image – not actual.National Highway Development Authority of India (NHAI) has taken up a project of constructing two four-lane flyovers of 500 m each. This package also involves construction of subways and other related works at Khanapara in Guwahati. The total cost of the project is Rs.2 billion.
Maheshwari Brothers Ltd. and the PSU, Telecommunication Consultant India Ltd (TCIL) are jointly executing the project. Rites India limited are the project consultant. These flyovers are part of the East-West Corridor (Porbandur-Silchar) under Package AS-03. This package involves widening and strengthening of existing National Highway from two-lane to four-lane from km.183.000 to km.163.895 of Guwahati to Sonapur section of NH-37 in Assam under Phase-II programme of NHDP.
The total work will take about two-and-half years to complete, says Vikash Narayan Bridge Engineer, RITES. The work on the flyovers has already been commenced in April this year and piling work is in progress, he said.