Illustrative image – not actual.
The Brihanmumbai Municipal Corporation (BMC) will begin excavation of twin tunnels under the Rs 14,000 crore Goregaon-Mulund Link Road (GMLR) project in early 2026, according to a senior official quoted by The Indian Express.
The launch shaft, now nearing completion despite monsoon conditions, is being constructed to deploy Tunnel Boring Machines (TBMs). Unlike the Mumbai Coastal Road Project, which used a single TBM for two tunnels, the GMLR will use two TBMs simultaneously. The first TBM, imported from Japan earlier this year, is being assembled and is expected to be operational by January 2025. The second TBM is expected to arrive by December.
The 12.2-km GMLR will connect Goregaon and Mulund via a high-speed corridor, with its key feature being a 6.65-km twin-tunnel running beneath Sanjay Gandhi National Park, at depths of 20 to 160 mtrs. Each tunnel, separated by 300 mtrs., will include six vehicular lanes, CCTV, firefighting systems, utility ducts, and rainwater harvesting infrastructure.