Twenty two per cent work completed on Uluberia water treatment plantIllustrative image – not actual.

Kolkata Metropolitan Water & Sanitation Authority has almost completed 22 per cent work on water treatment plant at Uluberia in Howrah district of West Bengal.

The project to be developed on turnkey basis involves design, construction and commissioning of 10 MGD capacity water treatment plant and 1.2 MG capacity underground reservoir-cum-booster pumping station. The company has appointed Sebabrata Bose Pvt Ltd, Kolkata as contractor for the project.

The project that is expected to cost Rs.14.16 crore is scheduled for completion by end of this year.