Illustrative image – not actual.The USD 1.5 billion project, being carried out by Chinese firm Sinohydro, entails addition of two power generating units; Unit-7 and 8 to the existing six units that were commissioned between 1983 and 1987.
As per the Zimbabwe Power Company (ZPC), most excavation work had been completed including the cooling tower, the boiler house and the chimney. Unit-7 is expected to start firing by April 2021 while Unit-8 will follow later on.
Hwange Power Station is Zimbabwe’s largest coal-fired power generator with production capacity of 920 MW. In addition to the Kariba South Hydro-power Extension Project, which was completed in March 2018, the Hwange expansion project is expected to substantially add to the national power grid.
