Illustrative image – not actual.The project worth Rs 1,166.26 crore is being developed under hybrid annuity mode (HAM). In March 2018, KNR Constructions bagged an order worth Rs 1,020.60 crore to execute the project.
In June 2018, KNR Srirangam Infra received sanction letter from banks to finance the project. The concession agreement was signed with the National Highways Authority of India (NHAI) for a period of 24 months.
In March 2019, KNR Srirangam Infra received appointed date from NHAI for the project.
As per the latest information available with Projects Today, around 25 percent work was completed. The project will be ready by June 2020.