Twenty five per cent work completed on Dhamra portIllustrative image – not actual.

Around 25 per cent project work on Phase I of  Dhamra port in Bhadrak district of Orissa is completed. The project is being implemented by a 50:50 joint venture of Larsen & Toubro and Tata Steel.

The project has received all statutory clearances including the environment clearance from the MoEF and the no objection certificate from the Pollution Control Board of the state.

The first phase will have two of the total 13 berths being developed with the northernmost being for liquid cargo, the southernmost for clean cargo and the middle berth for dry bulk cargo. The two berths will have basic loading-unloading facilities. Phase I of the project to cost Rs.2,463 crore is expected full completion by April 2010.

Also See:

Construction work begins at Dhamra Port (16-Nov-07)