TWAD Board has completed work on two of its major drinking water projects at Theni and Periyakulam in Tamil Nadu. Trial run will be conducted for Periyakulam project by 15 February 2016.
The speciality of the project is that electricity will not be required to pump water from head works to treatment plant as water will be drawn through natural gravity.
To scale down pressure in pipeline, break pressure tank of 60,000 litre capacity was constructed at the treatment plant. After the purification process, protected water will be stored in a 6 lakh litre capacity ground level sump and two over head tanks at Vadakarai and Thenikarai for distribution to residential areas. New pipeline was laid to cover a distance of 38 km so far and the rest 7 km will be covered shortly.
To augment water supply to Theni municipality, the TWAD board has been executing comprehensive drinking water project with Vaigai dam as its source at an estimated cost of Rs 68.83 crore. On completion, the TWAD board will supply 2.8 million litre of water to Theni municipality. Besides existing nine over head tanks, four new OHTs are being constructed at Balan Nagar, KRR Nagar, Karuvelnaickenpati and Kakkan Nagar.