Illustrative image – not actual.Tenughat Vidyut Nigam (TVNL) has planned to set up a
630 MW coal fired thermal power station at Tenughat, Lalpania in the Bokaro district
of Jharkhand.
The project envisages installation of 3 units of 210
MW each with associated infrastructures, machinery and equipment at an
estimated cost of Rs.2,047.33 crore.
Coal for the project would be procured from East and West
Bokaro coalfields under the Central Coalfields and also from some captive coal
mines, while water for the project would be sourced from the Tenughat reservoir
on the River Damodar.
On completion of the project, the power plant would generate 4,415 million units of electricity. The power generated from the plant would be supplied to the state electricity board and other agencies on demand. In case of surplus power, TVNL may sell power to other regions on demand.