Tuticorin Port to invest Rs.5,200 crore for expansionIllustrative image – not actual.

Tuticorin Port Trust (TPT) is planning to invest around Rs.5,200 crore to create additional capacity and infrastructure.

Of the total investment, around Rs.4,350 crore will be spent on the outer harbour development project, which will include two or three container terminals, one oil terminal, two coal terminal and a general cargo terminal. This part of the project will be executed in the PPP mode.

The inner harbour project, which will cost Rs.936 crore, will involve building of a coal berth and a general berth, and deepening of the draft from 10.7 m to 12.8 m to allow higher-capacity ships at the east cost port in Tamil Nadu. Of the total investment in the inner harbour, a major portion will be towards dredging, which is estimated to cost Rs.538 crore. Of this, Rs.350 crore will be funded by the port through its internal fund and the Centre will bear the balance. Dredging work is likely to be completed in 18 months.

The port had recently received in-principle approval from the Centre for two major projects involving the inner harbour and outer harbour. The projects, which will be executed through the PPP mode, are expected to be completed by 2012.

The expansion project will create an additional capacity of 40 million tpa by the end of 2012 and an additional four million tonnes will be added by 2017.