Illustrative image – not actual.The Mumbai Metro Rail Corporation (MMRC) is speeding up civil works for Metro-3 (Colaba-Bandra-Seepz) corridor.
The tunnel boring machines (TBMs) at work are now digging 100 ft per day from the initial 10 ft per day in November 2017.
MMRC aims to complete the tunnelling work for the 33.5 km corridor by March 2020. A total of 17 tunnel boring machines (TBMs) will be at work in Mumbai by June 2018.
The TBMs in main drive now include Vaitarna-1, which is set to bore a 4.5-km tunnel from Azad Maidan to Grant Road.
Krishna-1 and 2 will bore two parallel tunnels of 2.5 km each from Naya Nagar to Dadar Metro station; and Wainganga-1 at Pali ground, which is at work between Marol Naka and the Chhatrapati Shivaji International Airport. Till 3 April 2018, MMRC has achieved 1,267 mtr of tunnelling at various station sites.
The work on the corridor is running behind schedule by six months, which has escalated the cost by more than Rs 800 crore. The estimated cost of the project is Rs 23,136 crore.
Phase-I of the project, from Aarey to Bandra-Kurla Complex (BKC), will be operational by June 2021 and BKC to Cuffe Parade will be operational by December 2021.