Bengaluru Metro Rail’s tunnel boring machine (TBM) Varada, which was launched at the Rashtriya Military School station in Vellara in March 2021, has reached Langford Town Metro Station after completing tunneling works through 594 mtr length.
Another machine TBM Rudra, which was launched at South Ramp in April 2021, reached Dairy Circle Station after carrying out tunneling works through a distance of 614 mtr.
At present, the tunnel boring machine Rudra is driving through the station for further drive between Dairy Circle Metro station and Lakkasandra Metro station.
The tunnel boring machine Urja, which was drilling between Cantonment and Shivaji Nagar Metro stations, achieved a breakthrough in September 2021 in the presence of Chief Minister of Karnataka Basavaraj Bommai.
TBM Urja, drilling a length of 855 mtr for more than a year, was the first tunnel boring machine to achieve a breakthrough on Namma Metro’s Pink Line from Kalenga Agrahara to Nagawara (a distance of 21 km).
In August 2021, TBM Bhadra was drilling from Venkateshpura Metro station to the retrieval shaft (deep excavations that provide access points for tunnel boring machines) and has completed a length of 84 mtr.
TBM Tunga is drilling in the same direction and has completed a distance of 65.8 mtr. The tunnel boring machine Avni is drilling from Shivaji Nagar to Rashtriya Military School and has completed a distance of 636.6 mtr.
The TBM Lavi as well as TBM Vamikaare drilling in the same direction and these tunnel boring machines have completed 349.8 mtr and 140 mtr, respectively.