Tuirial hydro electricity project to be fully commissioned in NovIllustrative image – not actual.

The Tuirial hydro electricity project of 60 MW is expected be fully commissioned in November 2017.

The first unit of the project was technically commissioned in August 2017 and the second unit is expected to be commissioned by November 2017.

The original estimated cost for construction of the project was Rs 368.72 crore. However, the cost was revised to Rs 913.63 crore in the first estimate, and the second revised cost estimate jumped to Rs 1,329.43 crore.

The project was delayed in 2004 due to the issue of payment of compensation causing escalation in the cost of the project.

Mizoram will receive, free of cost, 12 percent of the energy generated from the project.

 